Storm Water Pollution Prevention Plan (SWPPP)
for
Small Construction Sites
*(Please note this document is intended for guidance only and does not ensure permit
compliance.)
• PROJECT NAME: Single Family Residence
• PROJECT SITE: XXXX Subdivision
• LOT #
Block
• ADDRESS of SITE:
• OWNER NAME and ADDRESS:
• OWNER TELEPHONE NUMBER:
• SITE AREA: Approximately X ft X X ft (0.5 acre) See the plot plan
• PROJECT DESCRIPTION:
A single-family house. XX bedrooms, XX bathrooms, Kitchen, Living Room, Game Room. Brick
and rock outside. Light excavation to remove trees and grade the lot for the construction of house.
After 80% of the house is complete the yard will be graded for driveway and landscaping at that
time Silt Fence will be removed.
• RUNOFF COFFICIENT:
0.3 – 0.5
• SEQUENCE OF ACTIVITIES:
Survey, Plot Plan, Building Permit, Storm Water Permit, Clear the Lot, Green Box (Toilet), Footing,
Foundation, Filling, Framing, Bricking, Gas and Electricity pipeline, Grading the lot, Landscaping,
and Final clean up
Storm Water Pollution Prevention Plan (SWPPP)
for
Small Construction Sites
*(Please note this document is intended for guidance only and does not ensure permit
compliance.)
• PROJECT NAME: Single Family Residence
• PROJECT SITE: XXXX Subdivision
• LOT #
Block
• ADDRESS of SITE:
• OWNER NAME and ADDRESS:
• OWNER TELEPHONE NUMBER:
• SITE AREA: Approximately X ft X X ft (0.5 acre) See the plot plan
• PROJECT DESCRIPTION:
A single-family house. XX bedrooms, XX bathrooms, Kitchen, Living Room, Game Room. Brick
and rock outside. Light excavation to remove trees and grade the lot for the construction of house.
After 80% of the house is complete the yard will be graded for driveway and landscaping at that
time Silt Fence will be removed.
• RUNOFF COFFICIENT:
0.3 – 0.5
• SEQUENCE OF ACTIVITIES:
Survey, Plot Plan, Building Permit, Storm Water Permit, Clear the Lot, Green Box (Toilet), Footing,
Foundation, Filling, Framing, Bricking, Gas and Electricity pipeline, Grading the lot, Landscaping,
and Final clean up
Storm Water Pollution Prevention Plan (SWPPP)
Page 2
• NAME OF RECEIVING STREAM:
Insert name of receiving stream.
• EXISTING SOIL INFORMATION
Insert type of soil.
• ENDANGERED SPECIES
This construction project is located in a developed subdivision; therefore, there are no endangered or
threatened species affected by the project.
• EROSION AND SEDIMENT CONTROLS:
Silt fence and Hay Bales will be installed as necessary to reduce or eliminate the runoff from the site
to the water of the state or municipal storm sewer. (See included map for the direction of the flow
and the erosion control measures used.)
• TIMING OF CONTROLS/MEASURES
Silt Fences and/or hay bale walls will be installed in areas where needed prior to clearing the lot.
When the site is stabilized (sod), silt fence and other erosion controls will be removed by the trash
company.
• WASTE MATERIALS:
Trash will be collected in the trash container on the site. The container will be emptied by the trash
company.
• SANITARY WASTE:
Portable Toilet from XXXX (Company Name) Rentals will be on the site after the clearing of the lot
and remain until 90% of job is complete. Service of the portable toilet will be done by the XXXX
Rentals.
• CONTROLS INSPECTION AND MAINTANCE PRACTIES:
Erosion controls will be inspected weekly or after any storm event of 0.5 inches or greater to make
sure the controls are in affect and do not require any maintenance. All erosion controls will be
maintained in good working order. Any repair or replacement will be done as soon as possible but
no later than 5 days after the inspection.
• NON-STORM WATER DISCHARGES: None
Storm Water Pollution Prevention Plan (SWPPP)
Page 3
• MATERIAL MANAGEMENT PRACTIES:
An effort will be made to store only enough products (Cements, sand, and dirt) to do the job. The
project superintendent will inspect daily to ensure all materials are on the site and not in the street.
• COMPLETION OF JOB:
After completion of the sewer line, water line, electricity line, and gas line the lot will be graded and
ready for landscaping. All erosion controls will be removed and the street will be cleaned to make
sure it is free of debris.
• Member of Company:
Name of the people on the job site and their position. Each of the members are allowed to make any
changes necessary to the erosion controls on the job site or this SWPPP.
• 303(d) list, TMDL, others:
Keep one of the following paragraphs whichever is applicable.
The storm water from the construction site discharges to XXXX (receiving stream). This water
body is not on the list of impaired water bodies (i.e., 303(d) list) for siltation/turbidity. Since this
water body is not impaired, a TMDL is not applicable to this construction project.
or
The storm water from the construction site discharges to XXXX (receiving stream). This water
body is on the list of impaired water bodies (i.e., 303(d) list) for siltation/turbidity. Even though this
project discharges to an impaired water body, a TMDL has not been written for the water body.
Therefore, a TMDL is not applicable to this construction project.
or
The storm water from the construction site discharges to XXXX (receiving stream). This water
body is on the list of impaired water bodies (i.e., 303(d) list) for siltation/turbidity. A TMDL has
been written for the water body that is applicable to the construction project. The following
information documents the construction projects compliance with the TMDL.
Must include documentation that the storm water discharges from the site will meet the applicable
TMDL guidelines.
Storm Water Pollution Prevention Plan (SWPPP)
Page 4
• CERTIFICATION:
I certify under penalty of law that this document and all the attachments were prepared under my
direction or supervision in accordance with Storm Water Permit Number ARR1500000. I am aware
that there are significant penalties for submission false information, including the possible of fine
and imprisonment for knowing violations.
Signed (Operator): _________________________
Position _________________
Singed (Member): _________________________
Position _________________
Signed(Member): __________________________ Position _________________
Storm Water Pollution Prevention Plan (SWPPP)
Page 5
Small Construction
Inspection Form
Name of Company:
Site Location:
Date
Location
Silt Fence
Hay Bales
Initial
Amount of
Time
Inspectors
Correction
OK?
OK?
Stabilization
Rain
Initials
OK?
(inches)
CERTIFICATION:
I certify under penalty of law that this document and all the attachments were prepared under my direction or supervision in accordance
with Storm Water Permit Number ARR1500000. I am aware that there are significant penalties for submission false information, including
the possible of fine and imprisonment for knowing violations.
Signed: __________________________________________
Title: _____________________________________________
Date: _____________________________________________