Instructions for Form F620-032-000 Boiler / Pressure Vessel / Water Heater Installation or Reinstallation Permit - Washington

Notification Icon This version of the form is not currently in use and is provided for reference only. Download this version of Instructions for Form F620-032-000 for the current year.

Instructions for Form F620-032-000 Boiler / Pressure Vessel / Water Heater Installation or Reinstallation Permit - Washington

This document contains official instructions for Form F620-032-000 , Boiler/Pressure Vessel/Water Heater Installation or Reinstallation Permit - a form released and collected by the Washington State Department of Labor and Industries. An up-to-date fillable Form F620-032-000 is available for download through this link.

FAQ

Q: What is Form F620-032-000?
A: Form F620-032-000 is a permit for the installation or reinstallation of a boiler, pressure vessel, or water heater in Washington.

Q: Who needs to use this form?
A: Anyone who is installing or reinstalling a boiler, pressure vessel, or water heater in Washington needs to use Form F620-032-000.

Q: Do I need a permit for installing a boiler, pressure vessel, or water heater?
A: Yes, you need a permit for installing or reinstalling a boiler, pressure vessel, or water heater in Washington.

Q: What information is required on the form?
A: The form requires information such as the type and size of the equipment, the location of the installation, the manufacturer's name and model number, and the installer's contact information.

Q: How long is the permit valid for?
A: The permit is valid for 90 days from the date of issuance.

Q: Are there any additional requirements for the installation?
A: Yes, there may be additional requirements depending on the specific equipment being installed. These requirements can be found in the Washington Administrative Code.

Q: What should I do after completing the form?
A: After completing the form, you need to submit it to the Washington State Department of Labor & Industries along with the required fee.

Q: Can I start the installation before obtaining the permit?
A: No, you cannot start the installation before obtaining the permit. The permit must be obtained before any work can begin.

ADVERTISEMENT

Instruction Details:

  • This 1-page document is available for download in PDF;
  • Actual and applicable for the current year;
  • Complete, printable, and free.

Download your copy of the instructions by clicking the link below or browse hundreds of other forms in our library of forms released by the Washington State Department of Labor and Industries.

Download Instructions for Form F620-032-000 Boiler / Pressure Vessel / Water Heater Installation or Reinstallation Permit - Washington

4.5 of 5 (25 votes)
  • Instructions for Form F620-032-000 Boiler / Pressure Vessel / Water Heater Installation or Reinstallation Permit - Washington, Page 1
ADVERTISEMENT